What happened
Protesters entered a data centre construction site in Amsterdam’s Westpoort district on 6 November. The Guardian reported that members of the Dutch direct action group Geef Tegengas climbed a crane, lit flares and attached helium balloons to equipment.S2S3S4
Police told Dutch broadcaster NOS that officers had tried to prevent the occupation and make arrests, but had been unable to stop the entry. They said force was used and one officer was slightly injured. Protesters said police used force and tear gas.S3
NOS reported on 7 November that a police spokesperson said all of the more than 200 detained protesters had been released. The supplied report does not establish whether any will face charges.R1
The entry was separate from a demonstration outside the fence associated with the Stop Dirty Data Centres campaign. That coalition said it had neither coordinated nor promoted the direct action. Microsoft said it respected peaceful protest but did not condone unlawful actions or conduct that put safety at risk.S3
Why it matters
The protest brings together objections to resource use and to Microsoft’s activities. The Guardian reported that banners opposed the company’s services to the Israeli military and US Immigration and Customs Enforcement. In April, the Dutch government told parliament that Microsoft would use all the planned server capacity, but said it had no information about the intended purposes or types of data.S3R5
The government acknowledged that the development uses land and electricity-grid capacity that affect other projects. It said the grid capacity had been contracted before congestion was declared and a queue introduced. The precise contract date was not public.R3
The planned grid connection is 99 megawatts, according to the government. Its calculation of about 0.87 terawatt-hours a year assumes continuous operation at that level; it is not a forecast of actual consumption. Separately, Statistics Netherlands recorded 5.09 billion kilowatt-hours delivered to Dutch data centres in 2024, equivalent to 4.6% of national electricity consumption.R4R7
The background
The government’s April parliamentary reply said the site’s building permit dated from 2020, before national restrictions on hyperscale data centres. It also said the project fell below those restrictions’ built-floor-area threshold. An appeal against environmental permits issued in 2025 remained underway when that reply was given.R2
A separate dispute concerns a letter circulated locally using Amsterdam’s logo. On 6 November, the municipality said the letter was not from the city and contained incorrect information, including a claim that the centre would prevent 30,000 homes from being built. Its notice did not identify the author.R6
The Amsterdam demonstrations coincided with a two-day European campaign seeking moratoria on new data centres. The Guardian reported smaller protests in Bristol, Berlin, Warsaw and Zagreb. Campaign coordinator Owen Espley said communities were being excluded from decisions about developments.S3
What happens next
Site owner Pure Data Centres asked those inside to leave safely and offered dialogue about the development. The supplied sources do not establish whether the November action delayed construction. Nor do they establish the current outcome of the environmental-permit appeal described in April.S3R2